North West England electrification schemes are a series of individual railway lines in North West England that have been, and continue to be electrified and upgraded. It is planned that these schemes will result in a modernised, cleaner, lower carbon and faster railway with improved capacity.
The 1955 Modernisation plan for the railways of the United Kingdom called for the phase out of steam traction.[1] Under this plan, parts of the railways in the northwest of England were electrified.[2][3]Crewe to Manchester Piccadilly and the Styal Line were completed very early on in this plan.[4] It also included the line from Crewe to Liverpool with Warrington Bank Quay, Wigan and Preston following in the early 1970s.[5] There was a pause in electrification projects in the late 1960s when money ran out but then the West Coast Main Line north of Weaver Junction through the northwest of England to just south of Glasgow was electrified progressively between 1970 and 1974.[6] The line from Preston to Blackpool was also proposed as a logical extension for electrification in conjunction with the Weaver Junction to Glasgow scheme in a document published by the British Railways Board in April 1968.[7] No further 25 kV AC activity occurred in the northwest until after 2009. There were some 3rd rail infill schemes though. In 1956, British Rail adopted 25 kV AC OHLE as standard for most electrification projects.[8] Some exceptions for 3rd rail extensions were allowed and confirmed by the ORR decades later.[9] Parts of the northwest had already been electrified with the 3rd rail system.
In 2007 Gordon Brown became Prime Minister and selected Andrew Adonis as Secretary of State for Transport. In 2009, Adonis in a government paper, put electrification back on the agenda and proposed infill electrification schemes in the North West of England as well as other railway electrification projects elsewhere.[10][11] As of 2022, electrification in Northwest England is ongoing with civil engineering works such as bridge rebuilding taking place between Bolton and Wigan (17 total)[12] and various other work is also in progress between Manchester Victoria and Stalybridge.[13][14]
The 2009 Adonis/DfT paper specifically stated that the work would commence immediately on the line between Liverpool and Manchester and a four-year time frame was given.[15] The first phase of the northwest project was to be between Manchester and Newton-le-Willows. This would allow diesel trains running between Glasgow and Edinburgh to Manchester Airport to be replaced by electric trains throughout via the West Coast Main Line.[16][17] Also reported in the paper was that the lines between Manchester and Preston and Liverpool and Preston were to be electrified.[18] Work was announced as having started in the Manchester area in March 2011.[19]
In July 2012 the coalition government announced new electrification schemes, all at 25 kV AC and reconfirmed schemes previously announced by Adonis.[20] These were: Electrification of the 'North West Triangle' (Manchester – Liverpool via Chat Moss, Huyton - Wigan, Manchester - Euxton Junction and Blackpool North – Preston); and part of the Northern Hub (New Ordsall Chord).[21][22] The North West triangle project called for a major civil engineering project to rebore the Farnworth tunnel on the Manchester–Preston line in advance of electrification.
In August 2013, the Department for Transport announced that the Windermere branch line between Oxenholme and Windermere was to be electrified by 2016.[23] However, the Hendy review[24] moved the completion of GRIP 3 to March 2017 with a yet to be determined date for completion of electrification.[25] In December 2013 it was announced that the line from Bolton to Wigan North Western would also be electrified by 2017.[26] However, the enhancements delivery plan update of September 2016 moved the completion date with only GRIP Stage 3 (Option selection) being completed by then.[27] On 1 September 2021, the Department for Transport formally announced this would now go ahead.[28]
In July 2017, Chris Grayling, the secretary of state for transport announced a number of electrification schemes were to be cancelled including the Lakes Line from Oxenholme to Windermere.[29]
In February 2019 the final electric test train ran on the Preston to Manchester line in readiness for squadron electric service.[30] In March 2019 the Railway Industry Association published a paper on Electrification cost challenge suggesting ways forward and a rolling program of electrification.[31] In April 2019 the power was switched on from Manchester Victoria to Miles Platting.[32] This section of line is now part of the Transpennine Route Upgrade though. Most of the schemes first planned in the 2010 timeframe are now complete.[33]
From December 2021 onwards, Wigan to Bolton electrification and associated works is in progress.[34] This will include Crow Nest Junction. This electrification scheme is claimed to also improve logistics and not have diesel trains running under the wires.[35] The National Electrification Efficiency Panel (NEEP) is involved in this scheme. This panel was commissioned by the Department for Transport at the end of 2021. and chaired by Professor Andrew McNaughton. It is claimed the civil engineering costs have already been halved.[36] As part of this schemes various bridges need to be completely demolished and rebuilt.[37][38][39] In August 2023 the principal contractor started liquidation proceedings and work on the scheme was halted.[40] The scheme is due for completion in 2025.[41]
In September 2020 the TDNS Traction Decarbonisation Network Strategy Interim Business case was published but dated July 31, 2020. The principal recommendation was further electrification of 13,000 km (single track kilometres) of UK railways. This document proposed a number of lines in the northwest for further electrification.[42] Page 213 had a list of suggestions including Liverpool to Manchester via Warrington and Chester to Warrington - often called the Cheshire Lines Committee railway lines. No attempt was made to prioritise the schemes in this publication.
As part of the Transport for Greater Manchester's Delivery Plan, proposals have been put forward to electrify the line between Manchester Victoria and Rochdale via Mills Hill. This is part of the 2040 Strategy, and they aim to complete business cases for the early delivery of it with potential delivery in 2026, subject to funding.[43]
The Northern Hub and the Great North Rail Project are railway schemes across Northern England that include electrifying lines in the northwest.[44][45] The original aim was to have series of upgrades that would reduce bottlenecks in the Manchester area.[46][47] The scheme also involved building and electrifying the Ordsall Chord to connect Manchester Victoria and Piccadilly stations.
The Manchester to Stalybridge scheme was originally part of Northwest England Electrification schemes but became part of Transpennine Route Upgrade.[48][49][50]
Northern Powerhouse Rail is also included in the plan.[55] It involves building less high-speed rail than previously proposed.[56] A link is introduced from HS2 to Liverpool via a section of new high speed line from reinstated low-level platforms at Warrington Bank Quay and onwards via upgraded sections to join the existing line to Liverpool Lime Street.[57][58]
^Nock, O.S. (1965). Britain's new railway: Electrification of the London-Midland main lines from Euston to Birmingham, Stoke-on-Trent, Crewe, Liverpool and Manchester. London: Ian Allan. OCLC59003738.
^Nock, O.S. (1974). Electric Euston to Glasgow. Ian Allan. ISBN978-0711005303.
^"Electric all the way"(PDF). Railways archive. May 1974. Archived(PDF) from the original on 11 June 2020. Retrieved 7 January 2022.
"On board with electrification". Permanent Way Institution Journal. 139 (1). January 2021. ISSN2057-2425 – via PWI.
Boocock, Colin (1991). East Coast Electrification. Ian Allan. ISBN0-7110-1979-7.
Nock, O.S. (1965). Britain's new railway: Electrification of the London-Midland main lines from Euston to Birmingham, Stoke-on-Trent, Crewe, Liverpool and Manchester. London: Ian Allan. OCLC59003738.
Nock, O.S. (1974). Electric Euston to Glasgow. Ian Allan. ISBN0-7110-0530-3.
Proceedings of the British Railways Electrification Conference, London 1960 - Railway Electrification at Industrial Frequency. London: British Railways Board. 1960.
Holt, Geoffrey O.; Biddle, Gordon (1986). The North West. A Regional history of the railways of Great Britain. Vol. 10 (2nd ed.). David St. John Thomas. ISBN978-0-946537-34-1.
Dyckhoff, Nigel (1999). Portrait of the Cheshire Lines Committee. Shepperton: Ian Allan Publishing. ISBN0711025215.