The MRT Pink Line (Thai: รถไฟฟ้ามหานคร สายสีชมพู) is an elevated monorail train line of the MRT in Bangkok and Nonthaburi Province, Thailand. The monorail line is 34.5 kilometres (21.4 mi) long and has 30 stations.[3] It runs in the northern part of the Bangkok Metropolitan Area from Nonthaburi Civic Center in Pak Kret district, Nonthaburi along the major east–west transport corridor of Highway 304 (Chaeng Wattana and Ram Inthra roads) to terminate at Min Buri in Min Buri district in east Bangkok. It opened for free public trial operation on 21 November 2023[4] with Prime Minister Srettha Thavisin taking the inaugural ride.[5]
The line is designed to link the northern areas of Bangkok and Nonthaburi by connecting with three existing and three future mass transit lines. At Nonthaburi Civic Center the line interchanges with the MRT Purple Line and the proposed MRT Brown Line. The line also interchanges with the SRT Dark Red Line, the BTS Sukhumvit Line and the planned BMA Grey Line. At the Min Buri terminus, the line interchanges with the MRT Orange Line.
Construction of the Pink Line began in December 2017. In October 2020, the BSR consortium stated that they aimed to open the first section of the Pink Line by October 2021, with services initially operating from Min Buri (PK30) to Government Complex (PK12). The complete line was originally set to be fully open by June 2022.[6] However, the outbreak of COVID-19 in Bangkok and changes to station locations delayed the opening date. On 24 September 2021, the MRTA Board granted a 290-day extension to the construction contract period.[7] In November 2021, the MRTA Board approved a new phased opening of the line starting from August 2022. On 9 December 2021, daily testing conducted at a maximum speed of 25 km/h (16 mph) began on a short 4 km (2.5 mi) section of the line between the depot at Min Buri and Bang Chan station. After a period of 3 months, testing was conducted at higher speeds and along a longer section of track.[8]
In April 2022, the acting Director-General of the Department of Rail Transport stated that the line would not begin full testing until September 2022 and that the first stage would not open until late December 2022.[9] In May 2023, a further 345-day extension was announced by the MRTA, delaying the start of trial operations for the initial section and later the final opening of the full line to June 2024.[10] However, after the opening of the MRT Yellow line the BSR announced that the first section of the line would open in November 2023.[11]
The line opened for free public trial operation on 21 November 2023 and officially launched on 18 December 2023.[4] Revenue service was initially scheduled to begin on 3 January 2024,[12] but an incident involving conductor rails resulted in a delay to 7 January, with a 15 percent discount for travels between Royal Irrigation Department and Min Buri, and the first four stations will be free of charge, running only in one direction on rails unaffected by the incident as a shuttle service, while the affected rails are being repaired.[13]
The line begins at Nonthaburi Civic Center near Khae Rai Junction, Nonthaburi Province, in the northwest of Greater Bangkok. The line then heads north along Tiwanon Road to Pak Kret Intersection, Pak Kret District, before turning east to run along Chaeng Watthana road. It interchanges with the SRT Dark Red Line at Lak Si Station and passes over Vibhavadi Rangsit Road running east through the Ram Intra intersection and the Lak Si monument in Bang Khen District, where it crosses under the BTS Sukhumvit Line and interchanges with Wat Phra Sri Mahathat. The line then continues farther east along Ram Inthra Road to the northeast of Bangkok before terminating at Min Buri where it finally interchanges with the MRT Orange Line at Min Buri station (OR28).
The Pink Line was first proposed in 2005 by the Office of Transport and Traffic Policy and Planning as a heavy rail underground line. It was changed to a monorail line in 2008 to reduce construction costs. The director-general of the Office of Transport and Traffic Policy and Planning had previously stated in an interview that the Pink Line was considered a priority scheme to be completed by 2017–18, as it ran past the then recently opened Bangkok Government Complex.[14] A review was undertaken in early 2012 to reconsider the heavy rail option, but cost restraints prevailed and the Office decided to continue with the monorail plan. The review of the line did result, however, in the addition of 6 new stations. The environmental impact assessment for the Pink Line was finalized in late 2012. In October 2012, members of the new government requested to extend the planned line east by 3.4 km (2.1 mi) beyond the Min Buri terminus to Nong Chok.[15] However, this extension of the line was not approved. The expected cost of the line in 2012 with the additional 6 extra stations was 55 billion baht.[16]
The Pink line was due to be tendered in the third quarter of 2013 with construction due to commence in early 2014.[17] However, delays in preparation of the tender in relation to the selection of monorail rolling stock and political protests resulting in a snap national election in early Feb 2014 further delayed the Pink Line tender.[18] A coup in May 2014 resulted in a new military administration and the tender being deferred while a review of all mass transit projects was undertaken for a period of 18 months. The Pink line tender was then changed to a PPP tender process which was not released until mid 2016.
The BSR consortium consisting of BTS Group Holdings (75% majority stake) with Sino-Thai Engineering and Construction (STEC), and Ratch Group (RATCH) won the bid in early December 2016 to construct and operate the Pink Line.[19] The BSR consortium won the bid for a 30-year concession operate the line and also won the bid to build and operate the MRT Yellow Line.
On 16 June 2017, contracts were signed by the BSR consortium with the Mass Rapid Transit Authority of Thailand.[20] The BSR established the Northern Bangkok Monorail Company Limited (NBM) to operate the line.
Construction of the Pink Line began in December 2017 with the BSR consortium establishing a number of preparation work sites and closing lanes along the east-west Chaeng Wattana-Ram Inthra corridor.[21] By 30 September 2018, overall construction was 10.37% complete.[22] Construction work on Tiwanon Road began at the end of October 2018 with the temporary closure of long stretches of the middle lanes between Khae Rai and Pak Kret intersections. Construction had progressed to 31.46% complete by the end of March 2019.[23] By the end of July 2019, completion of civil constructions had further progressed to 40.13%.[24] Overall construction was 48.15% complete at the end of November 2019.[25]
By the end of January 2020, construction had progressed to 51.96%.[26] By the end of May 2020, construction had progressed to 58.78%.[27] At the end of July 2020, construction had progressed to 61.83%.[28] At the end of September 2020, construction was 66.31% complete.[29] Construction was 70.32% complete by the end of December 2020.[30] Construction progress was 74.14% complete by the end of February 2021.[31] Construction progress was 77.57% complete by the end of April 2021.[32]
The terminus station at Nonthaburi Civic Center (PK01) was moved 337 m (1,106 ft) closer to the Esplanade Cineplex at Khae Rai junction due to objections from civil servants working at the Nonthaburi provincial office who were concerned that their view of the outside would be obstructed. A new EIA was completed for the relocation, but the new station location required Cabinet approval, causing delays to the opening of this section of the line.[6] Nopparat station (PK26) has also been moved 313 metres (1,027 ft) away from Nopparat Rajathanee hospital due to the construction of a new Department of Highways bridge. The Cabinet agreed to the amended EIA for the relocation of both stations on 20 October 2020.[33] On 24 September, the MRTA Board granted a 290-day extension to the construction contract schedule due to station design changes at Noppharat Ratchathani station (PK26) due to a new overpass plan, the relocation of Nonthaburi Civic Center station (PK01) and a flood mitigation project by the Highway Department impacting on the construction timeline of Laksi District (PK13), Chaeng Watthana Government Complex (PK 12) and Chaeng Watthana 14 stations (PK 11).[7]
By the end of November 2021, construction progress was 84.45%.[34] On 9 December 2021, daily testing conducted at a maximum speed of 25 km/h (16 mph) began on a short 4 km (2.5 mi) section of the line from the depot at Minburi to Bang Chan station. After a period of 3 months, testing was then conducted at higher speeds along a longer section of the line.[8] By the end of March 2022, construction progress was at 86.51%. At the end of January 2023, civil works construction had progressed to 94.93%.[35]
By the end of May 2023, construction had progressed to 86.57%.[36] By August 2023, construction had further progressed to 97.54%.[37]
In 2016, the BTSC received a fund for an extension to link Impact, Muang Thong Thani and the Muang Thong Thani condominium buildings from Bangkok Land Public Company Limited. Accordingly, the BSR joint venture proposed a 2.8 km (1.7 mi), 2 station spur monorail route to link to Impact, Muang Thong Thani from what was then Si Rat station (now Muang Thong Thani station; the names were later switched).[38] The two stations will be located adjacent to the Impact Challenger building near Muang Thong Thani Lake and the Impact Forum. In early August 2018, a second public hearing was conducted by the MRTA into the extension proposal.[39]
The spur line proposal required a new EIA, which was completed in August 2020.[40] The proposal was then presented to the Cabinet for approval to commence construction before the end of 2020.[41] On 22 October 2020, the National Environment Board chaired by the Deputy PM approved the EIA and the MRTA evaluated construction costs of the spur line with BSR, with the final proposal proposed to be presented to Cabinet for approval by the end of November 2020.[42] On 9 February 2021, Cabinet approved the 2.8 km (1.7 mi) spur line which is expected to cost 3.37 billion baht.[43] Construction of the spur line was due to commence in July 2021. However, due to COVID-19 outbreaks in greater Bangkok construction was delayed until after December 2021. Finally, on 20 June 2022 the MRTA issued a Notice to Proceed for the now 4.2 billion baht spur line and soon after construction commenced.[44]
By the end of January 2023, civil works construction had progressed to 16.15%.[45] By the end of May 2023, construction had progressed to 27.77%.[36]
The MRTA may also consider a further 2 km (1.2 mi) extension in the future from Muang Thong Thani to Tiwanon road.[46]
The BSR selected Bombardier Innovia Monorail 300 rolling stock for the Pink Line. The BSR announced that they will purchase 42 four-car sets to operate the line.[47] The total order of 70 sets of trains for the Pink and Yellow lines will cost 50 billion baht. These trains will be manufactured by CRRC Puzhen Bombardier Transportation Systems (joint venture of Bombardier Transportation and CRRC Nanjing Puzhen) in Wuhu, Anhui, China. The first set was shipped on 4 September 2020[48] and arrived in Thailand on 1 October at Laem Chabang port with a handover ceremony attended by the Thai Prime Minister, the Bangkok Mass Transit System PLC. (BTSC) Chairman, MRTA and the Canadian Ambassador to Thailand.[49] By July 2021, 8 sets had been delivered and were being tested.[50] All sets were due to be delivered by early 2022. However, as of mid-April 2022, only 24 sets had been received and were progressively undergoing testing.[9] The remaining sets were expected to be delivered by July 2022, but this was later delayed with the last sets delivered by early March 2023.[51]
Technical Characteristics
[53] Innovia Monorails are all fully automated and are equipped with CITYFLO 650 communications-based train control for driverless operation to increase reliability, shorten head ways between trains and lower maintenance costs.[54]
The Bombardier Innovia Monorail 300 operates on a narrow, elevated guide beam. Pre-cast, post-tensioned guide beams are constructed at an off-site location and later installed on the system. The guide beams are 690 mm (27 in) wide. The Innovia Monorail 300 was designed to navigate curves as tight as 46 m (151 ft) and a maximum grade of 6%. Monorail switches will be either beam replacement or multi-position pivot switches.[55] The system will have evacuation walkways down the entire length of the guide beam. These walkways will allow passengers to escape onboard hazards. These walkways will be used by the maintenance crew for repairs and general maintenance to the system.[56]
Originally, the line was designed with 24 stations, two of which with a park and ride facility. However, six new stations were added in mid-2012 for a total of 30 stations.
Code | Station Name[57] | Opened | Platform
Type |
Transfer | Notes | |
---|---|---|---|---|---|---|
English | Thai | |||||
PK 01 | Nonthaburi Civic Center | ศูนย์ราชการนนทบุรี | 21 November 2023 | Side | Connecting station to MRT and MRT (future). | Exit to: • National Broadcasting and Telecommunications Commission • Nonthaburi Civic Center • Esplanade Cineplex Ngamwongwan – Khae Rai • Siam Business Administration Nonthaburi Technological College • Makut Rommayasaran Park |
PK 02 | Khae Rai | แคราย | Side | Exit to: • Central Chest Institute of Thailand • Lotus's Rattanathibet • Nonthaburi Provincial Transport Office | ||
PK 03 | Sanambin Nam | สนามบินน้ำ | Side | Exit to: • Tansamrit Wittaya School • Army Quartermaster Department | ||
PK 04 | Samakkhi | สามัคคี | Side | Exit to: • Flea Market - Pakret District • Chonlaprathan Songkro School | ||
PK 05 | Royal Irrigation Department | กรมชลประทาน | Side | Exit to: • Royal Irrigation Department • Chonprathan Wittaya School • Wat Cholpratarn Rangsarit • Panyananthaphikkhu Medical Center • Club Golf Course Irrigation | ||
PK 06 | Yaek Pak Kret | แยกปากเกร็ด | Side | Exit to Major Hollywood Pak Kret | ||
PK 07 | Pak Kret Bypass | เลี่ยงเมืองปากเกร็ด | Side | Exit to: • Big C Extra Chaeng Watthana 2 (Pak Kret) • HomePro Chaeng Watthana | ||
PK 08 | Chaeng Watthana - Pak Kret 28 | แจ้งวัฒนะ-ปากเกร็ด 28 | Side | Exit to: • Central Chaengwattana • Software Park Thailand • Panyapiwat Institute of Management • THE TARA CP ALL | ||
PK 09 | Si Rat | ศรีรัช | Island | Exit to: • Thai Watsadu Chaengwattana • Muang Thong Thani | ||
PK 10 | Muang Thong Thani | เมืองทองธานี | Side & Island | Cross-platform interchange with Impact Spur Line (under construction). | Exit to Makro Chaeng Watthana | |
PK 11 | Chaeng Watthana 14 | แจ้งวัฒนะ 14 | Side | Exit to: • Mongkutwattana Hospital • Big C Chaengwatthana 1 (Laksi) • Charn at The Avenue Chaengwatthana • TK. Palace Hotel & Convention • 11th Military District • Lotus's Chaengwattana | ||
PK 12 | Government Complex | ศูนย์ราชการเฉลิมพระเกียรติ | Side | Exit to: • Ministry of Justice • 1st Long Range Reconnaissance Company • 1st Air Defence Brigade • Administrative Court of Thailand • Department of Consular Affairs • Department of Special Investigation • Bangkok North Municipal Court • Central Bankruptcy Court • Royal Thai Armed Forces Headquarters • Office of the Comptroller General • Centara Life Government Complex Hotel & Convention Centre Chaeng Watthana • Immigration Division 1 • Vayupak Convention Centre | ||
PK 13 | National Telecom | โทรคมนาคมแห่งชาติ | Side | Exit to: • National Telecom Public Company Limited • Na-Nakorn Building • Lak Si District Office • Regional Office of NBTC 1 | ||
PK 14 | Lak Si | หลักสี่ | Side | Connecting station to SRT . | Exit to: • IT Square Lak Si • Rattanakosin Technological College • Center for Biologics Research and Development (CBRD) • Chulabhorn Graduate Institute • Chulabhorn Hospital • Chulabhorn Research Institute | |
PK 15 | Rajabhat Phranakhon | ราชภัฏพระนคร | Side | Exit to: • Phranakhon Rajabhat University • MaxValu Supermarket Laksi | ||
PK 16 | Wat Phra Sri Mahathat | วัดพระศรีมหาธาตุ | Side | Interchange station with BTS . | Exit to: • Bang Khen District Office • Metropolitan Health and Wellness Institution • Wat Phra Sri Mahathat Woramahawihan • Metropolitan Waterworks Authority Bang Khen • Krirk University • Thai Niyom Songkhrao School • Wat Pra Sri Mahathat Secondary Demonstration School, Phranakhon Rajabhat University | |
PK 17 | Ram Inthra 3 | รามอินทรา 3 | Side | Exit to: • Central Ramindra • KMB hospital • Royal Thai Army Golf Course | ||
PK 18 | Lat Pla Khao | ลาดปลาเค้า | Side | Exit to Big C Extra Ram Inthra | ||
PK 19 | Ram Inthra Kor Mor 4 | รามอินทรา ก.ม.4 | Side | Exit to Foodland Ram Inthra | ||
PK 20 | Maiyalap | มัยลาภ | Side | Exit to Office Of Inspector General | ||
PK 21 | Vacharaphol | วัชรพล | Side | Connecting station to MRL (future) | Exit to: • Liab Duan Market • Vachara Phirom Park | |
PK 22 | Ram Inthra Kor Mor 6 | รามอินทรา ก.ม.6 | Side | Exit to: • Saiaksorn School • Triamwit Pattana, Pre-Medical School | ||
PK 23 | Khu Bon | คู้บอน | Side | |||
PK 24 | Ram Inthra Kor Mor 9 | รามอินทรา ก.ม.9 | Side | Exit to Synphaet Ramintra Hospital | ||
PK 25 | Outer Ring Road - Ram Inthra | วงแหวนรามอินทรา | Side | Exit to: • Fashion Island • The Promenade | ||
PK 26 | Nopparat | นพรัตน์ | Side | Exit to: • Nopparat Rajathanee Hospital • Siam Amazing Park • Boromrajonani College of Nursing Napparat Vajira | ||
PK 27 | Bang Chan | บางชัน | Side | |||
PK 28 | Setthabutbamphen | เศรษฐบุตรบำเพ็ญ | Side | Exit to Setthabutbamphen School | ||
PK 29 | Min Buri Market | ตลาดมีนบุรี | Side | Exit to: • Chatuchak Weekend Market (Minburi) • Minburi Market • Minburi Technical College • Bangkok Social Security Office Area 10 • Navamin 9 Hospital | ||
PK 30 | Min Buri | มีนบุรี | Side | Interchange station with MRT (under construction) | ||
Impact Spur Line (under construction) | ||||||
MT01 | Impact Muang Thong Thani | อิมแพ็คเมืองทองธานี | 2025 | Island | Exit to: • IMPACT Arena • Kasikorn Business Technology Group • Wat Phasuk Maneechak • Sukhothai Thammathirat Open University | |
MT02 | Lake Muang Thong Thani | ทะเลสาบเมืองทองธานี | Side | Exit to: • IMPACT Speed Park • Thunder Dome Stadium • Immigration Bureau • ibis Bangkok IMPACT • Novotel Bangkok IMPACT • Cyber Crime Investigation Bureau |
MRT Pink Line headway[58] | |
---|---|
Time | Headway (Minutes:Seconds) |
Monday - Friday | |
06.00 - 06.30 | 10:00 |
06:30 - 08:30 | 05:00 |
08:30 - 16:30 | 10:00 |
16:30 - 19:30 | 05:00 |
19:30 - 24:00 | 10:00 |
Saturday to Sunday and Public Holiday | |
06:00 - 24:00 | 10:00 |
MRT Pink Line Ridership[59] | |||||
---|---|---|---|---|---|
Year | Quarter | Quarterly Ridership | Daily Ridership | Annual Ridership | Remarks |
2024 | Q1 | 4,698,403 | 51,631 | 14,829,674 | PK 01 Nonthaburi Civic Centre - PK 30 Min Buri section officially opened on 7 January 2024. |
Q2 | 4,671,647 | 51,337 | |||
Q3 | 5,459,624 | 59,344 | As of September 2024. | ||
Q4 |
During the free trial period on 24 December 2023 at approximately 4:45 a.m., before daily passenger service had begun, an estimated 300m stretch of electrified conductor rail fell down to the road below near Samakkhi station, with an additional 4km of the conductor rail left hanging above the street.[60] Three cars were damaged, and a train became stuck on the damaged section. No injuries were reported.[61][62] All stations between Nonthaburi Civic Center and Pak Kret Bypass were closed, and a shuttle service was provided between Chaeng Watthana - Pak Kret 28 and National Telecom stations, while an investigation took place and the conductor rail was repaired.[63]
At 6:00 p.m. on 30 December, the seven stations reopened, with trains running in a single direction between Nonthaburi Civic Center and Royal Irrigation Department stations on the unaffected rails as a shuttle service, and in both directions on the remaining stations.[13][64]
On 30 March 2024 during construction of the Muang Thong Thani branch line, cement fell from the concourse of Impact Muang Thong Thani Station, breaking a car window and injuring a child riding in the back seat. The Minister of Transport ordered a 7-day halt to construction in the area.[65]