South Station Tower | |
---|---|
General information | |
Status | Under construction, funded[2] |
Type | Office, residential[1] |
Location | Atlantic Avenue, Boston, Massachusetts, United States |
Construction started | January 2020[2] |
Estimated completion | 2025[4] |
Height | |
Roof | 690 ft (210 m)[3] |
Technical details | |
Floor count | 51 |
Design and construction | |
Architect(s) | César Pelli[5] |
Developer | Hines Interests[5] |
South Station Tower is a skyscraper under construction in Boston, Massachusetts, the high-rise portion of a three-building development. Construction on Phase 1 of the project, a 51-story, 678-foot tower with offices and condominiums, started in January 2020 and is expected to take four years.[2] It will be built atop Boston's historic South Station complex, an example of transit-oriented development. The overall project will include condominium units, office space, a parking structure, and possibly hotel space.[6] The property was initially proposed by Hines Interests and TUDC, a subsidiary of Tufts University.
Part of Phase I, an expanded bus station, will use a foundation put in place when the station was last renovated in the late 1980s.[7] The high-rise tower will be supported by a new foundation constructed in the area between the existing station and the tracks. Foot traffic will be rerouted around construction areas.[8]
South Station Tower was planned to break ground in 2008, with completion scheduled to occur in 2010, but the project stalled. Approval has been obtained for a project totaling 2,190,000 square feet (203,000 m2).[9] As of March 2016 the developer's website was updated stating the tower would begin construction early in 2017;[10] the FAA had given approval in February for a tower reaching 677 feet (206 m)}.[11] The developer's rights to build on the site were scheduled to expire in April 2017,[12] but the state extended them until the end of the year.[13] Construction was halted due to MBTA concerns,[citation needed] but Hines did not stop the project.
Development of the airspace above the southbound tracks has been delayed several times. The building was conceived by Tufts president Jean Mayer, who foresaw an "epicenter of high-profile medical research" in downtown Boston. In 1991, Tufts created a for-profit development subsidiary, TUDC LLC, and acquired the rights to the airspace. Development over the past decade has been complicated by Boston waterfront zoning restrictions, which require pedestrian access to the waterfront. In 1997, TUDC brought on Hines Interests LP as a development partner. In 2006, TUDC and Hines filed a Development Plan for the project.[14]
Questions were raised in 2007 about the university's role in the project,[15] and Tufts withdrew in 2009.[16]
South Station Tower was originally designed with a height of 759 feet (231 m), which included a decorative spire.[1] However, the project was downscaled in 2006.[1]
In July 2016, the developer filed a "Notice of Project Change"[17] with the Boston Planning and Development Agency (BPDA), proposing a number of changes in the project, including the addition of more residential space.[6] The notice included a timeline calling for construction of the project's first building, the high-rise tower, to begin in 2017. In December 2016, the board of the BPDA approved construction of the project.[18] It was delayed to December 2017, then delayed again to 2018 due to MBTA rights.[clarification needed] Construction officially began in February 2020, with a five year completion timeline.
On March 21, 2024, a steel beam fell from the top of the tower, damaging several windows, before coming to rest on the ninth floor.[19] Some equipment from the worksite also fell, landing at street-level. The MBTA, who owns South Station and the South Station Bus Terminal, suspended commuter services and ordered work to halt in the time after the incident. No injuries were reported, but construction company Suffolk agreed to pause work while investigations proceeded.[20]
Construction work resumed March 27, 2024 following the conclusion of the stop-work order and subsequent investigations by OSHA.[21]
On April 9th 2024, A few weeks after the beam fell, a fire was started outside the ninth floor by welders.[22] The fire was quickly put out and the site was again shut down for a safety review, reopening on April 10th 2024 [23]
Preliminary design was done by architect Cesar Pelli, whose designs are reminiscent of his Wells Fargo Center in Minneapolis. The structure has been LEED pre-certified "silver" and won the EPA's "Green design" award.[24][25]
{{cite web}}
: CS1 maint: unfit URL (link)